Third winter suspension
Works were suspended on 27 December 2025 as part of scheduling the execution stages; the previously quoted end-2025 delivery passed without handover.
Everything we publish, dated, newest first: project updates we verified at their official sources, changes to project facts (prices, number of units, handover date) and each city’s monthly price index release. Every item leads to its full page.
Works were suspended on 27 December 2025 as part of scheduling the execution stages; the previously quoted end-2025 delivery passed without handover.
Akarat24 updated two listings: a duplex at $175,000 ($30,000 down) and a villa at $200,000 ($40,000 down), balance over one year, delivery end-2025.
A Facebook promotional post presented the compound and its facilities with delivery stated as end-2025; a commenter questioned the date.
Syria and Qatar sign a USD 4 billion agreement to build a third passenger terminal at Damascus International Airport.
Works resumed after weather improved, on 3 May 2025.
First international commercial flight (Qatar Airways from Doha) lands at Damascus International Airport, the airport nearest the project.
Works were suspended for the winter season because of weather conditions.
Site works resumed on 20 May 2024.
Rebuilding Syria (stated last update 22 Feb 2024) describes core concrete structures erected, interior brick partitioning started on several blocks, and sewage, underground electrical and internal-road works being executed.
Project announcement recorded on 22 February 2024 (Q1 2024) as a 22,000 m² gated villa complex in Aqraba, with Imtilak Real Estate as the announcing party.
Works were suspended due to bad weather and its effect on concrete works.
Site access was granted and the works commencement order issued on 1 October 2023.
The Swiss Village project licence was issued on 24 July 2023, per the timeline on the developer's site.